Five months have passed since the opening of the Taigene complex building. Time flies. At present, the construction of the main structure has been completed. At this stage, the task is to build wall masonry, as well as hydropower installation projects. Strive for completion by the end of 2021.
During the period, Taigene drawings made a major change, the original plan of the second floor canteen to the first floor, convenient for restaurant staff to transport vegetables and sundries. The follow-up work of the comprehensive building is the installation of elevators, the preparation of canteen equipment, the installation of office air conditioning, the introduction of natural gas in the canteen, the decoration and construction of indoor and outdoor walls, and the final acceptance procedures.